Task Dependencies

Dependencies allow you to define the order in which tasks must be completed. A task with dependencies won't be selected for execution until all its dependencies are closed.

How Dependencies Work

When cub selects the next task to run, it:

  1. Finds all tasks with status == "open"
  2. Filters to tasks where all dependencies are closed
  3. Sorts remaining tasks by priority (P0 first)
  4. Selects the first one
flowchart LR
    A[Task A<br/>open] --> B[Task B<br/>open]
    B --> C[Task C<br/>open]

    style A fill:#4CAF50,color:white
    style B fill:#FFC107
    style C fill:#FFC107

In this diagram:

  • Task A is ready (no dependencies)
  • Task B depends on A (blocked until A closes)
  • Task C depends on B (blocked until B closes)

Blocked vs Ready Tasks

Ready tasks have:

  • Status of open
  • All dependencies closed (or no dependencies)

Blocked tasks have:

  • Status of open
  • One or more dependencies that are not closed

Check which tasks are ready:

# Beads backend
bd ready

# Or with cub
cub run --ready

Setting Up Dependencies

Beads Backend

Beads uses a blocks field (inverse of dependsOn):

# Task B depends on Task A
# Read as: "B is blocked by A"
bd dep add task-B task-A --type blocks

# View a task's dependencies
bd show task-B --json | jq '.blocks'

Remove a dependency:

bd dep remove task-B task-A

JSON Backend

Use the dependsOn array:

{
  "tasks": [
    {
      "id": "myproj-001",
      "title": "Design database schema",
      "status": "open",
      "dependsOn": []
    },
    {
      "id": "myproj-002",
      "title": "Implement user model",
      "status": "open",
      "dependsOn": ["myproj-001"]
    },
    {
      "id": "myproj-003",
      "title": "Add user API endpoints",
      "status": "open",
      "dependsOn": ["myproj-002"]
    }
  ]
}

Dependency Patterns

Sequential Chain

Tasks must execute in strict order:

flowchart LR
    A[Design] --> B[Implement] --> C[Test] --> D[Deploy]
# Beads
bd dep add task-B task-A --type blocks
bd dep add task-C task-B --type blocks
bd dep add task-D task-C --type blocks

Fan-Out (Parallel)

Multiple tasks can run after a common prerequisite:

flowchart LR
    A[Design API] --> B[Backend]
    A --> C[Frontend]
    A --> D[Mobile]

All three implementation tasks become ready once "Design API" closes. Cub runs them one at a time by priority, but they don't block each other.

{
  "tasks": [
    {"id": "api-001", "title": "Design API", "dependsOn": []},
    {"id": "api-002", "title": "Backend implementation", "dependsOn": ["api-001"]},
    {"id": "api-003", "title": "Frontend implementation", "dependsOn": ["api-001"]},
    {"id": "api-004", "title": "Mobile implementation", "dependsOn": ["api-001"]}
  ]
}

Fan-In (Merge)

A task that requires multiple prerequisites:

flowchart LR
    A[Backend] --> D[Integration Tests]
    B[Frontend] --> D
    C[Mobile] --> D

"Integration Tests" only becomes ready when all three implementations are closed.

{
  "id": "api-005",
  "title": "Integration tests",
  "dependsOn": ["api-002", "api-003", "api-004"]
}

Diamond Pattern

Combining fan-out and fan-in:

flowchart LR
    A[Design] --> B[Backend]
    A --> C[Frontend]
    B --> D[Integration]
    C --> D
{
  "tasks": [
    {"id": "t-001", "title": "Design", "dependsOn": []},
    {"id": "t-002", "title": "Backend", "dependsOn": ["t-001"]},
    {"id": "t-003", "title": "Frontend", "dependsOn": ["t-001"]},
    {"id": "t-004", "title": "Integration", "dependsOn": ["t-002", "t-003"]}
  ]
}

Priority vs Dependencies

Dependencies always take precedence over priority.

Even if Task A is P4 (lowest) and Task B is P0 (critical), if B depends on A, then A runs first.

{
  "tasks": [
    {"id": "t-001", "title": "Setup infrastructure", "priority": "P4", "dependsOn": []},
    {"id": "t-002", "title": "Critical feature", "priority": "P0", "dependsOn": ["t-001"]}
  ]
}

Execution order: t-001 then t-002 (despite P0 priority).

Use Priority for Independent Tasks

Priority determines order among tasks that are both ready. Use it to prioritize unrelated work, not to override dependencies.

Example Workflow: Feature Development

A typical feature implementation:

flowchart TD
    A[spec] --> B[design]
    B --> C[implement-model]
    B --> D[implement-api]
    C --> E[implement-ui]
    D --> E
    E --> F[write-tests]
    F --> G[documentation]
# Create tasks
bd create "Write feature spec" --type task -p 1
bd create "Design architecture" --type task -p 2
bd create "Implement data model" --type task -p 2
bd create "Implement API endpoints" --type task -p 2
bd create "Implement UI components" --type task -p 2
bd create "Write integration tests" --type task -p 3
bd create "Update documentation" --type task -p 4

# Set up dependencies
bd dep add cub-002 cub-001 --type blocks
bd dep add cub-003 cub-002 --type blocks
bd dep add cub-004 cub-002 --type blocks
bd dep add cub-005 cub-003 --type blocks
bd dep add cub-005 cub-004 --type blocks
bd dep add cub-006 cub-005 --type blocks
bd dep add cub-007 cub-006 --type blocks

Avoiding Circular Dependencies

Circular dependencies create a deadlock where no task can run:

flowchart LR
    A --> B --> C --> A

Cub doesn't explicitly detect cycles, but you'll notice when cub run --ready returns no tasks despite open work.

To fix:

  1. Identify the cycle:

    bd list --status open --json | jq '.[].blocks'
    

  2. Remove one dependency to break the cycle:

    bd dep remove task-C task-A
    

Gates and Checkpoints

Use gate type tasks for manual approval points:

{
  "id": "t-gate-001",
  "title": "Security Review Checkpoint",
  "type": "gate",
  "status": "open",
  "dependsOn": ["t-003", "t-004"]
}

Downstream tasks depend on the gate:

{
  "id": "t-005",
  "title": "Deploy to production",
  "dependsOn": ["t-gate-001"]
}

The gate blocks production deployment until manually closed:

# After security review passes
bd close t-gate-001 -r "Security review approved by team lead"

Debugging Dependencies

See What's Blocking

# Beads
bd show task-id --json | jq '.blocks'

# JSON
jq '.tasks[] | select(.id == "task-id") | .dependsOn' prd.json

Find All Blocked Tasks

# Tasks that have unfulfilled dependencies
cub run --ready  # Shows only ready tasks

# Compare with all open
bd list --status open  # Shows all open tasks

Visualize Dependencies

For complex graphs, export and visualize:

# Generate DOT format
bd list --json | jq -r '
  .[] |
  . as $task |
  (.blocks // [])[] |
  "\($task.id) -> \(.)"
' | sort -u > deps.dot

# Wrap with digraph header
echo "digraph deps {" > graph.dot
cat deps.dot >> graph.dot
echo "}" >> graph.dot

# Render with graphviz
dot -Tpng graph.dot -o dependencies.png

Best Practices

  1. Keep chains short: Long dependency chains delay execution. Parallelize where possible.

  2. Use epics for grouping, dependencies for ordering: Don't use dependencies just to group related tasks.

  3. Document non-obvious dependencies: If the dependency isn't clear from task titles, add a note explaining why.

  4. Validate early: Run cub run --ready before starting to catch missing dependencies.

  5. Avoid micro-dependencies: Don't create dependencies between tiny tasks that could be combined.